Herschel Lessons Learned Meeting: "Operations from Cradle to Grave"Reports of Session Moderators:==> Concluding Reports of Session Moderators | ||||||||
Changed: | ||||||||
< < | Record a "Lesson" HERE (no longer open for additions):==> http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons | |||||||
> > | Record a "Lesson" HERE (no longer open for additions):==> http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons | |||||||
A cross-correlation between "Lessons" and Sessions can be found here :==> http://herschel.esac.esa.int/twiki/bin/view/HSC/LessonSessions |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Added: | ||||||||
> > | Reports of Session Moderators:==> Concluding Reports of Session Moderators | |||||||
Changed: | ||||||||
< < | Record a "Lesson" HERE :==> http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons | |||||||
> > | Record a "Lesson" HERE (no longer open for additions):==> http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons | |||||||
A cross-correlation between "Lessons" and Sessions can be found here :==> http://herschel.esac.esa.int/twiki/bin/view/HSC/LessonSessions | ||||||||
Line: 19 to 20 | ||||||||
| ||||||||
Deleted: | ||||||||
< < | Late Registrations of representatives of other projects are being accepted. These may contact L. Metcalfe directly to register, or follow the instructions below. | |||||||
1. Top-level objectives for the end-May 2013 Lessons Learned Meeting |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 41 to 41 | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave"Record a "Lesson" HERE :==> http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons | ||||||||
Added: | ||||||||
> > | ||||||||
Added: | ||||||||
> > | A cross-correlation between "Lessons" and Sessions can be found here :==> http://herschel.esac.esa.int/twiki/bin/view/HSC/LessonSessions | |||||||
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 39 to 39 | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 39 to 39 | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
|
Line: 1 to 1 | |||||||||
---|---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | |||||||||
Line: 9 to 9 | |||||||||
| |||||||||
Changed: | |||||||||
< < |
| ||||||||
> > |
| ||||||||
| |||||||||
Changed: | |||||||||
< < |
| ||||||||
> > |
| ||||||||
| |||||||||
Changed: | |||||||||
< < | Registrations will be accepted up to May 13 | ||||||||
> > | Late Registrations of representatives of other projects are being accepted. These may contact L. Metcalfe directly to register, or follow the instructions below. | ||||||||
1. Top-level objectives for the end-May 2013 Lessons Learned Meeting |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 39 to 39 | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 32 to 32 | ||||||||
3. Registration | ||||||||
Added: | ||||||||
> > | ||||||||
4. Accommodation & Transportation | ||||||||
Added: | ||||||||
> > |
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > | Record a "Lesson" HERE :==> http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons
| |||||||
| ||||||||
Line: 12 to 17 | ||||||||
| ||||||||
Added: | ||||||||
> > | Registrations will be accepted up to May 13 | |||||||
Deleted: | ||||||||
< < | * NO ABSTRACT :==> Record a "Lesson" instead !!! HERE :==> *http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessonsTABLE OF CONTENTS
| |||||||
Added: | ||||||||
> > | 1. Top-level objectives for the end-May 2013 Lessons Learned Meeting
| |||||||
Changed: | ||||||||
< < | Scope and goalsProgramme for the MeetingObjectives of the Lessons Learned exerciseTop-level objectives for the end-May 2013 Lessons Learned Meeting
| |||||||
> > |
| |||||||
| ||||||||
Changed: | ||||||||
< < |
| |||||||
> > | 2. Programme for the Meeting, and methodology | |||||||
Changed: | ||||||||
< < | Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30)* | |||||||
> > | 3. Registration | |||||||
Changed: | ||||||||
< < | The details will be elaborated as material is submitted. [Material = Abstracts or "Lessons" submitted to the above-described repository (or one of its ICC equivalents).] | |||||||
> > | 4. Accommodation & Transportation | |||||||
Changed: | ||||||||
< < | The overall Mission design concept and methodology• Mission Design & Technical drivers (incl. orbit, space environment, lifetime, science data bandwidth, ACMS & pointing, DTCP/GS, …) • Structure of the Science Ground Segment (SGS), division of responsibilities, and organisation • Concept of Smooth Transitions • (Herschel Common Science System) HCSS - Concept, development, and components (MDB, CUS, HSpot, Configuration Control, Build System, System Integration, Testing and Validation) • Calibration (Standards & modeling; Cross-calibration: Herschel-Herschel, Herschel-other missions) Operations Processes and Procedures• Operations preparations • Support to instrument level tests • End-to-end tests and simulations • LEOP and Commissioning Phase * Calibration, in-flight performance, evaluation, verification, and optimisation • PV Phase * AOT-release, calibration, in-flight performance, evaluation, verification, and optimisation • Science Demonstration Phase * KP-release, A&A Special Issue, information provision for AO-1 • Routine Science Phase * Calibration, in-flight performance, evaluation, verification, and optimisation * Scheduling strategy, policies, flexibility, re-planning * Community Support - Level of service provided to community (excl. downlink) * Helpdesk * Information provision (documentation, mailings, and web) * Workshops (uplink/HSpot, downlink/HIPE, topical) * Observing programme maintenance/replanning, programme conflicts & optimisation, duplications tools, HOTAC tools, HOTAC meetings * Downlink (other than DP and Archive) * Mission DataBase (MDB) / Versant ... Data processing• Providing data to observers - pipeline processing, standard products, HSA population, on demand reprocessing, and interactive data processing • HIPE provision - design rationale, technical choices (Java, Jython), scope, implementation, ... • HIPE use - performance, user friendliness & support, interaction with other packages, ... Herschel Science Archive (HSA)• User friendliness and support , HSA population, on-demand reprocessing, interaction with other archives & VO Science Management• Amount of GT, proprietary time • Concept of Key Programme • Concept of Science Demonstration Phase (SDP) • Scheduling philosophy ("best use of helium" as the principal driver) • Handling of calibration observationsMethodology of the exercise
Programme for the MeetingRegistration & Abstract SubmissionAccommodation & Transportation | |||||||
> > |
Line: 1 to 1 | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave"
| |||||||||||||
Changed: | |||||||||||||
< < |
| ||||||||||||
> > |
| ||||||||||||
* NO ABSTRACT :==> Record a "Lesson" instead !!! HERE :==> * | |||||||||||||
Line: 51 to 55 | |||||||||||||
• Structure of the Science Ground Segment (SGS), division of responsibilities, and organisation • Concept of Smooth Transitions • (Herschel Common Science System) HCSS - Concept, development, and components (MDB, CUS, HSpot, Configuration Control, Build System, System Integration, Testing and Validation) | |||||||||||||
Changed: | |||||||||||||
< < | • Calibration (Standards & modelling; cross-calibration: Herschel-Herschel, Herschel-other missions) | ||||||||||||
> > | • Calibration (Standards & modeling; Cross-calibration: Herschel-Herschel, Herschel-other missions) | ||||||||||||
Operations Processes and Procedures |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 26 to 26 | ||||||||
Scope and goals | ||||||||
Added: | ||||||||
> > | Programme for the Meeting | |||||||
Objectives of the Lessons Learned exercise
Top-level objectives for the end-May 2013 Lessons Learned Meeting | ||||||||
Line: 107 to 109 | ||||||||
| ||||||||
Changed: | ||||||||
< < | Agenda | |||||||
> > | Programme for the Meeting | |||||||
Registration & Abstract Submission |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 41 to 41 | ||||||||
Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30)* | ||||||||
Changed: | ||||||||
< < | The details will be elaborated as material is submitted. [Material = Abstracts or, for other LL suggestions contact a HSC Group Leader for your area of interest, or your ICC Manager.] | |||||||
> > | The details will be elaborated as material is submitted. [Material = Abstracts or "Lessons" submitted to the above-described repository (or one of its ICC equivalents).] | |||||||
The overall Mission design concept and methodology |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 7 to 8 | ||||||||
| ||||||||
Added: | ||||||||
> > |
* NO ABSTRACT :==> Record a "Lesson" instead !!! HERE :==> *http://herschel.esac.esa.int/twiki/bin/view/HSC/HerschelLessons | |||||||
TABLE OF CONTENTS
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | ||||||||
Line: 11 to 11 | ||||||||
| ||||||||
Changed: | ||||||||
< < | (The Science Operations Coordination Group will assess the inputs received on May 7) | |||||||
> > | (The Science Operations Coordination Group will assess the inputs received on May 7. Registrations will be accepted up to May 13.) | |||||||
Scope and goals | ||||||||
Line: 36 to 36 | ||||||||
The overall Mission design concept and methodology• Mission Design & Technical drivers (incl. orbit, space environment, lifetime, science data bandwidth, ACMS & pointing, DTCP/GS, …) | ||||||||
Changed: | ||||||||
< < | • Structure of SGS, division of responsibilities, and organisation | |||||||
> > | • Structure of the Science Ground Segment (SGS), division of responsibilities, and organisation | |||||||
• Concept of Smooth Transitions | ||||||||
Changed: | ||||||||
< < | • HCSS - Concept, development, and components (MDB, CUS, HSpot, Configuration Control, Build System, System Integration, Testing and Validation) | |||||||
> > | • (Herschel Common Science System) HCSS - Concept, development, and components (MDB, CUS, HSpot, Configuration Control, Build System, System Integration, Testing and Validation) | |||||||
• Calibration (Standards & modelling; cross-calibration: Herschel-Herschel, Herschel-other missions) | ||||||||
Line: 62 to 62 | ||||||||
| ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
| |||||||
Data processing | ||||||||
Line: 80 to 80 | ||||||||
Science Management• Amount of GT, proprietary time | ||||||||
Changed: | ||||||||
< < | • Concept of KP • Concept of SDP • Scheduling philosophy ("best use of helium" the principal driver) | |||||||
> > | • Concept of Key Programme • Concept of Science Demonstration Phase (SDP) • Scheduling philosophy ("best use of helium" as the principal driver) | |||||||
• Handling of calibration observations
Methodology of the exercise
| ||||||||
Added: | ||||||||
> > | (Registrations will be accepted up to May 13.) | |||||||
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Changed: | ||||||||
< < | Herschel Lessons Learned Meeting: 28-30 May 2013 | |||||||
> > | Herschel Lessons Learned Meeting: "Operations from Cradle to Grave" | |||||||
| ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
| |||||||
| ||||||||
Line: 18 to 18 | ||||||||
Objectives of the Lessons Learned exercise | ||||||||
Changed: | ||||||||
< < | The top-level objectives for the end-May 2013 Lessons Learned Meeting are: | |||||||
> > | Top-level objectives for the end-May 2013 Lessons Learned Meeting | |||||||
| ||||||||
Line: 78 to 77 | ||||||||
• User friendliness and support , HSA population, on-demand reprocessing, interaction with other archives & VO | ||||||||
Changed: | ||||||||
< < | Science management | |||||||
> > | Science Management | |||||||
• Amount of GT, proprietary time • Concept of KP |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 7 to 7 | ||||||||
| ||||||||
Added: | ||||||||
> > | TABLE OF CONTENTS
| |||||||
DEADLINE for ABSTRACTS: eob May 6 2013 (The Science Operations Coordination Group will assess the inputs received on May 7) |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 29 to 29 | ||||||||
Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30)* | ||||||||
Changed: | ||||||||
< < | The details will be elaborated as material is submitted. [Material = Abstracts or, for other LL suggestions contact an HSC Group Leader for your area of interest, or your ICC Manager.] | |||||||
> > | The details will be elaborated as material is submitted. [Material = Abstracts or, for other LL suggestions contact a HSC Group Leader for your area of interest, or your ICC Manager.] | |||||||
The overall Mission design concept and methodology |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 97 to 97 | ||||||||
Agenda | ||||||||
Changed: | ||||||||
< < | Registration | |||||||
> > | Registration & Abstract Submission | |||||||
Accommodation & Transportation |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 8 to 8 | ||||||||
| ||||||||
Changed: | ||||||||
< < | DEADLINE for ABSTRACTS: eob May 6 2013 | |||||||
> > | DEADLINE for ABSTRACTS: eob May 6 2013 (The Science Operations Coordination Group will assess the inputs received on May 7) | |||||||
Scope and goals | ||||||||
Line: 28 to 29 | ||||||||
Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30)* | ||||||||
Changed: | ||||||||
< < | The details will be elaborated as material [Abstracts or other LL suggestions (contact an HSC Group Leader for your area of interest)] is submitted. | |||||||
> > | The details will be elaborated as material is submitted. [Material = Abstracts or, for other LL suggestions contact an HSC Group Leader for your area of interest, or your ICC Manager.] | |||||||
The overall Mission design concept and methodology |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 7 to 7 | ||||||||
| ||||||||
Added: | ||||||||
> > | DEADLINE for ABSTRACTS: eob May 6 2013 | |||||||
Scope and goalsObjectives of the Lessons Learned exercise | ||||||||
Changed: | ||||||||
< < | The top-level objectives for the end-May 2013 Lessons Learned Meeting are: • Capture the good, the bad, and the ugly. * In particular "best practices" to be passed on for future missions but should also document particular problems and in general important experience. • Generate conclusions and recommendations based on the above. • Propagate the above LL output (into ESA and towards future missions) as appropriate. • Generate a written Report and presentation(s). | |||||||
> > | The top-level objectives for the end-May 2013 Lessons Learned Meeting are:
| |||||||
Changed: | ||||||||
< < | Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30) | |||||||
> > |
Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30)* | |||||||
The details will be elaborated as material [Abstracts or other LL suggestions (contact an HSC Group Leader for your area of interest)] is submitted. | ||||||||
Added: | ||||||||
> > |
The overall Mission design concept and methodology | |||||||
Deleted: | ||||||||
< < | • The overall Mission design concept and methodology | |||||||
• Mission Design & Technical drivers (incl. orbit, space environment, lifetime, science data bandwidth, ACMS & pointing, DTCP/GS, …) • Structure of SGS, division of responsibilities, and organisation • Concept of Smooth Transitions • HCSS - Concept, development, and components (MDB, CUS, HSpot, Configuration Control, Build System, System Integration, Testing and Validation) • Calibration (Standards & modelling; cross-calibration: Herschel-Herschel, Herschel-other missions) | ||||||||
Changed: | ||||||||
< < | • Operations Processes and Procedures | |||||||
> > |
Operations Processes and Procedures | |||||||
• Operations preparations • Support to instrument level tests • End-to-end tests and simulations • LEOP and Commissioning Phase | ||||||||
Changed: | ||||||||
< < | • Calibration, in-flight performance, evaluation, verification, and optimisation | |||||||
> > |
| |||||||
• PV Phase | ||||||||
Changed: | ||||||||
< < | • AOT-release, calibration, in-flight performance, evaluation, verification, and optimisation | |||||||
> > |
| |||||||
• Science Demonstration Phase | ||||||||
Changed: | ||||||||
< < | • KP-release, A&A Special Issue, information provision for AO-1 | |||||||
> > |
| |||||||
• Routine Science Phase | ||||||||
Changed: | ||||||||
< < | • calibration, in-flight performance, evaluation, verification, and optimisation • scheduling strategy, policies, flexibility, re-planning • Community Support - Level of service provided to community (excl. downlink) • Helpdesk • Information provision (documentation, mailings, and web) • Workshops (uplink/HSpot, downlink/HIPE, topical) • Observing programme maintenance/replanning, programme conflicts & optimisation, duplications tools, HOTAC tools, HOTAC meetings • Downlink (other than DP and Archive) • MDB / Versant ... • Data processing | |||||||
> > |
Data processing | |||||||
• Providing data to observers - pipeline processing, standard products, HSA population, on demand reprocessing, and interactive data processing • HIPE provision - design rationale, technical choices (Java, Jython), scope, implementation, ... • HIPE use - performance, user friendliness & support, interaction with other packages, ... | ||||||||
Changed: | ||||||||
< < | • Herschel Science Archive (HSA) | |||||||
> > |
Herschel Science Archive (HSA) | |||||||
• User friendliness and support , HSA population, on-demand reprocessing, interaction with other archives & VO | ||||||||
Changed: | ||||||||
< < | • Science management | |||||||
> > |
Science management | |||||||
• Amount of GT, proprietary time • Concept of KP • Concept of SDP |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 78 to 78 | ||||||||
Agenda | ||||||||
Changed: | ||||||||
< < | List of Participants | |||||||
> > | Registration | |||||||
Accommodation & Transportation |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 9 to 9 | ||||||||
Scope and goals | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > | Objectives of the Lessons Learned exercise
The top-level objectives for the end-May 2013 Lessons Learned Meeting are: • Capture the good, the bad, and the ugly. * In particular "best practices" to be passed on for future missions but should also document particular problems and in general important experience. • Generate conclusions and recommendations based on the above. • Propagate the above LL output (into ESA and towards future missions) as appropriate. • Generate a written Report and presentation(s).Outline scope for the "Operations from Cradle to Grave" LL Meeting (May 28-30) The details will be elaborated as material [Abstracts or other LL suggestions (contact an HSC Group Leader for your area of interest)] is submitted. • The overall Mission design concept and methodology • Mission Design & Technical drivers (incl. orbit, space environment, lifetime, science data bandwidth, ACMS & pointing, DTCP/GS, …) • Structure of SGS, division of responsibilities, and organisation • Concept of Smooth Transitions • HCSS - Concept, development, and components (MDB, CUS, HSpot, Configuration Control, Build System, System Integration, Testing and Validation) • Calibration (Standards & modelling; cross-calibration: Herschel-Herschel, Herschel-other missions) • Operations Processes and Procedures • Operations preparations • Support to instrument level tests • End-to-end tests and simulations • LEOP and Commissioning Phase • Calibration, in-flight performance, evaluation, verification, and optimisation • PV Phase • AOT-release, calibration, in-flight performance, evaluation, verification, and optimisation • Science Demonstration Phase • KP-release, A&A Special Issue, information provision for AO-1 • Routine Science Phase • calibration, in-flight performance, evaluation, verification, and optimisation • scheduling strategy, policies, flexibility, re-planning • Community Support - Level of service provided to community (excl. downlink) • Helpdesk • Information provision (documentation, mailings, and web) • Workshops (uplink/HSpot, downlink/HIPE, topical) • Observing programme maintenance/replanning, programme conflicts & optimisation, duplications tools, HOTAC tools, HOTAC meetings • Downlink (other than DP and Archive) • MDB / Versant ... • Data processing • Providing data to observers - pipeline processing, standard products, HSA population, on demand reprocessing, and interactive data processing • HIPE provision - design rationale, technical choices (Java, Jython), scope, implementation, ... • HIPE use - performance, user friendliness & support, interaction with other packages, ... • Herschel Science Archive (HSA) • User friendliness and support , HSA population, on-demand reprocessing, interaction with other archives & VO • Science management • Amount of GT, proprietary time • Concept of KP • Concept of SDP • Scheduling philosophy ("best use of helium" the principal driver) • Handling of calibration observationsMethodology of the exercise
| |||||||
Agenda |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Changed: | ||||||||
< < |
| |||||||
> > |
| |||||||
|
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 15 to 15 | ||||||||
List of Participants | ||||||||
Changed: | ||||||||
< < | Accomodation | |||||||
> > | Accommodation & Transportation |
Line: 1 to 1 | ||||||||
---|---|---|---|---|---|---|---|---|
Herschel Lessons Learned Meeting: 28-30 May 2013 | ||||||||
Line: 7 to 7 | ||||||||
| ||||||||
Added: | ||||||||
> > | Scope and goals
| |||||||
Agenda | ||||||||
Changed: | ||||||||
< < | Registration | |||||||
> > | List of Participants | |||||||
Accomodation | ||||||||
Deleted: | ||||||||
< < |
OrganisationMeeting SummaryScope and goals
|